Baker Cranes was selected to design and build cranes which ranged from 10t to 50t capacity for NZ’s largest construction project – Waterview Connection.
The cranes were purpose-built to handle each of the 24000 10t segments needed for the twin 2.4 km tunnels.
Cranes commissioned between May 2013 & October 2013.
Scope of Works:
- 3 off 50t x 5m+30m+5m Portal Cranes
- 2 off 50t x 23m Portal Cranes
- 2 off 20t x 24.5m Double Girder EOT Cranes
- 2 off 10t x 24.5m Single Girder EOT Cranes
See the Videos section to see the Load Test Video of the first 50t Portal Crane.